Written by Claude on 2026-10-10 at the maintainer's request from the spec's plan (section 4), the GitHub milestones and the repository history.
Plan and actuals¶
| Milestone | Planned due | Exit test (spec) | Status on 2026-10-11 |
|---|---|---|---|
| M0 | 18 Oct | A PX4 SITL vehicle flies a survey via MAVSDK from a script | Engineering done 8 to 9 Oct. Product docs v1 edited by the maintainer; issue 1 can close |
| M1a | 25 Oct | Nominal and jamming recordings committed | Done 9 Oct, as JSON-lines recordings with ground truth, not ROS 2 bags |
| M1b | 1 Nov | NT-01 and NT-02 pass on recordings | Done 9 Oct |
| M2a | 8 Nov | A three-vehicle survey completes nominally | Done 9 Oct, with backend and audit log |
| M2b | 15 Nov | Approve and deny visible in the audit log; C2-01 passes | Done 9 to 10 Oct |
| M3 | 22 Nov | Results table generated by one command and checked in CI | Done 10 Oct, plus a held-out validation |
| M4a | 29 Nov | Usability session, short findings note | Round 1 done 11 Oct (2 participants, found a blocker); protocol v2 and a console redesign made; round 2 (2 to 3 participants) planned |
| M4b | 6 Dec | Demo video, README polish, write-up, v1.0 tag | Repository public, docs site live, README summary, demo video recorded and release notes written; v1.0 tag next |
The re-plan, honestly¶
Nothing slipped. The engineering milestones were finished far ahead of their dates, in about three days of repository history (the maintainer planned over about three weeks beforehand). The remaining schedule risk is people and writing time, not engineering: the usability sessions, the product documents, the video and the write-up.
Scope changes made on the way, with reasons:
- No ROS 2. The spec allows falling back to MAVSDK only. Recordings are JSON lines.
- PX4 pinned to an unreleased main commit, because GPS failure injection for Gazebo does not
exist in v1.17.0 or v1.18.0-rc1.
- LAND for a frozen position, after ground truth showed the vehicle flies away (ADR 0003).
- A calibrated position bound, after NT-03 turned out not to be met (PR 37).
- Added: a held-out validation, ground truth, a requirements trace with a test.
- Not done: link_loss scenario, a noise or offset injector for gradual drift, reuse of the
approval pattern from personal-ai, mission-completion measurement.
Next¶
Maintainer: product docs, risk log and weekly status, usability sessions, "How this was built".
Agent: the video support and README after the sessions. Sector-completion tracking and the
fleet-level mission-completion measurement are done (eval/fleet/results.md).